Preparing cost estimates for a well and getting management approval in the form of an AFE is the final step in well planning. The AFE is often accompanied by a projected payout schedule or revenue forecast. Although an essential part of well planning, the cost estimate is often the most difficult to obtain with any degree of reliability.  
Preparing cost estimates for a well and getting management approval in the form of an AFE is the final step in well planning. The AFE is often accompanied by a projected payout schedule or revenue forecast. Although an essential part of well planning, the cost estimate is often the most difficult to obtain with any degree of reliability.


==Overview==
== Overview ==


A properly prepared well cost estimate may require as much engineering work as the well design. The costs should address dry holes and completed wells. In addition, accounting considerations such as tangible and intangible items must be taken into account. Unfortunately, many cost “guestimates” are the “back of the napkin” type, with only a small amount of engineering work used in the process.  
A properly prepared well cost estimate may require as much engineering work as the well design. The costs should address dry holes and completed wells. In addition, accounting considerations such as tangible and intangible items must be taken into account. Unfortunately, many cost “guestimates” are the “back of the napkin” type, with only a small amount of engineering work used in the process.


The cost estimate is the last item to be considered in the well plan, because it is heavily dependent on the technical aspects of the projected well. After the technical aspects are established, the expected time required to drill the well must be determined. The actual well cost is obtained by integrating expected drilling and completion times with the well design.
The cost estimate is the last item to be considered in the well plan, because it is heavily dependent on the technical aspects of the projected well. After the technical aspects are established, the expected time required to drill the well must be determined. The actual well cost is obtained by integrating expected drilling and completion times with the well design.


==Factors/cost estimates evaluated in an AFE==
== Factors/cost estimates evaluated in an AFE ==


The following are some of the major cost estimates captured in the AFE:
The following are some of the major cost estimates captured in the AFE:


* [[AFE: projected drilling time|Projected drilling time]]
*[[AFE:_projected_drilling_time|Projected drilling time]]
* [[AFE: projected drilling time|Time categories/ time considerations]]
*[[AFE:_projected_drilling_time|Time categories/ time considerations]]
* [[AFE: location preparation|Location preparation]]
*[[AFE:_location_preparation|Location preparation]]
* [[AFE: drilling rig and tools|Drilling rig and tools]]
*[[AFE:_drilling_rig_and_tools|Drilling rig and tools]]
* [[AFE: drilling fluids|Drilling fluids]]
*[[AFE:_drilling_fluids|Drilling fluids]]
* [[AFE: rental equipment|Rental equipment]]
*[[AFE:_rental_equipment|Rental equipment]]
* [[AFE: cementing|Cementing]]
*[[AFE:_cementing|Cementing]]
* [[AFE: support services|Support services]]
*[[AFE:_support_services|Support services]]
* [[AFE: transportation|Transportation]]
*[[AFE:_transportation|Transportation]]
* [[AFE: supervision and administration|Supervision and administration]]
*[[AFE:_supervision_and_administration|Supervision and administration]]
* [[AFE: tubulars|Tubulars]]
*[[AFE:_tubulars|Tubulars]]
* [[AFE: wellhead equipment|Wellhead equipment]]
*[[AFE:_wellhead_equipment|Wellhead equipment]]
* [[AFE: completion equipment|Completion equipment]]
*[[AFE:_completion_equipment|Completion equipment]]


==Cost estimate categories==
== Cost estimate categories ==


Engineering considerations include:
Engineering considerations include:


* Dry-hole and completed costs
*Dry-hole and completed costs
* Logical grouping, such as completion equipment or tubular goods
*Logical grouping, such as completion equipment or tubular goods
* Convenience groupings, such as rental equipment
*Convenience groupings, such as rental equipment


Accounting considerations include:
Accounting considerations include:


* Tangible items
*Tangible items
* Intangible items
*Intangible items
* contingency items
*contingency items


The sample AFE summary in '''Fig. 1''' illustrates several cost categories.
The sample AFE summary in '''Fig. 1''' illustrates several cost categories.


<gallery widths=300px heights=200px>
<gallery widths="300px" heights="200px">
File:Devol2 1102final Page 499 Image 0001.png|'''Fig. 1—Summary of the authority for expenditure.'''
File:Devol2 1102final Page 499 Image 0001.png|'''Fig. 1—Summary of the authority for expenditure.'''
</gallery>
</gallery>


===Tangible and intangible costs===
=== Tangible and intangible costs ===


Accounting and tax principles treat tangible and intangible costs in different ways. As a result, they must be segregated in the cost estimate. Although intangible costs are difficult to define precisely, they include expenditures incurred by the operator for:
Accounting and tax principles treat tangible and intangible costs in different ways. As a result, they must be segregated in the cost estimate. Although intangible costs are difficult to define precisely, they include expenditures incurred by the operator for:


* Labor
*Labor
* Fuel
*Fuel
* Repairs
*Repairs
* Hauling
*Hauling
* Supplies
*Supplies


These expeditures are generally used for:
These expeditures are generally used for:


* Drilling, perforating, and cleaning wells.
*Drilling, perforating, and cleaning wells.
* Preparing the surface site prior to drilling.
*Preparing the surface site prior to drilling.
* Construction derricks, tanks, pipelines, and other structures erected in connection with drilling, but not including the cost of the materials themselves.
*Construction derricks, tanks, pipelines, and other structures erected in connection with drilling, but not including the cost of the materials themselves.


The fundamental test is defining the salvage value of the item. If the item does not have a salvage value, it is an intangible.  
The fundamental test is defining the salvage value of the item. If the item does not have a salvage value, it is an intangible.


Intangible drilling and development costs do not include the following:
Intangible drilling and development costs do not include the following:
* Tangible property ordinarily considered as having salvage value.
* Wages, fuel, repairs, hauling, supplies, etc., in connection with equipment facilities or structures not incident to or necessary for the drilling of wells, such as structures for storing oil.
* Casing, even though required by state law.
* Installation of production facilities.
* Oilwell pumps, separators, or pipelines.


===Detailed cost analysis===
*Tangible property ordinarily considered as having salvage value.
It is usually desirable to provide more cost detail than the general summary in '''Fig. 1'''. A sample of a detailed summary is shown in '''Fig. 2'''. Engineers wishing to evaluate detailed cost analysis worksheets should refer to Ref. 1.  
*Wages, fuel, repairs, hauling, supplies, etc., in connection with equipment facilities or structures not incident to or necessary for the drilling of wells, such as structures for storing oil.
*Casing, even though required by state law.
*Installation of production facilities.
*Oilwell pumps, separators, or pipelines.


Factors considered in the detailed cost analysis will be presented in the [[Authority for expenditures (AFE)|AFE page]]. The cost divisions presented in '''Fig. 1''' will be used. These factors are heavily dependent on company drilling philosophy and, as such, may not apply to all companies.
=== Detailed cost analysis<ref name="r1">Adams, N. and Charrier, T. 1985. ''Drilling Engineering: A Complete Well Planning Approach''. Tulsa, Oklahoma: PennWell Publishing Company.</ref> ===


<gallery widths=300px heights=200px>
It is usually desirable to provide more cost detail than the general summary in '''Fig. 1'''. A sample of a detailed summary is shown in '''Fig. 2'''.&nbsp;
 
Factors considered in the detailed cost analysis will be presented in the '''AFE page'''. The cost divisions presented in '''Fig. 1''' will be used. These factors are heavily dependent on company drilling philosophy and, as such, may not apply to all companies.
 
<gallery widths="300px" heights="200px">
File:Devol2500.png|'''Fig. 2—AFE detailed summary.'''
File:Devol2500.png|'''Fig. 2—AFE detailed summary.'''
</gallery>
</gallery>


==References==
== References ==
1. Adams, N. and Charrier, T. 1985. ''Drilling Engineering: A Complete Well Planning Approach''. Tulsa, Oklahoma: PennWell Publishing Company.
 
<references />


== Noteworthy papers in OnePetro ==
== Noteworthy papers in OnePetro ==
Line 87: Line 89:
== External links ==
== External links ==


==See also==
== See also ==
[[Well planning]]


[[PEH:Introduction to Well Planning]]
[[Well_planning|Well planning]]


[[Category: 1.1.2 Authority for expenditures (AFE)]]
[[PEH:Introduction_to_Well_Planning]]
[[Category:1.1.2 Authority for expenditures (AFE)]]

Revision as of 11:23, 25 June 2015

Preparing cost estimates for a well and getting management approval in the form of an AFE is the final step in well planning. The AFE is often accompanied by a projected payout schedule or revenue forecast. Although an essential part of well planning, the cost estimate is often the most difficult to obtain with any degree of reliability.

Overview

A properly prepared well cost estimate may require as much engineering work as the well design. The costs should address dry holes and completed wells. In addition, accounting considerations such as tangible and intangible items must be taken into account. Unfortunately, many cost “guestimates” are the “back of the napkin” type, with only a small amount of engineering work used in the process.

The cost estimate is the last item to be considered in the well plan, because it is heavily dependent on the technical aspects of the projected well. After the technical aspects are established, the expected time required to drill the well must be determined. The actual well cost is obtained by integrating expected drilling and completion times with the well design.

Factors/cost estimates evaluated in an AFE

The following are some of the major cost estimates captured in the AFE:

Cost estimate categories

Engineering considerations include:

  • Dry-hole and completed costs
  • Logical grouping, such as completion equipment or tubular goods
  • Convenience groupings, such as rental equipment

Accounting considerations include:

  • Tangible items
  • Intangible items
  • contingency items

The sample AFE summary in Fig. 1 illustrates several cost categories.

Tangible and intangible costs

Accounting and tax principles treat tangible and intangible costs in different ways. As a result, they must be segregated in the cost estimate. Although intangible costs are difficult to define precisely, they include expenditures incurred by the operator for:

  • Labor
  • Fuel
  • Repairs
  • Hauling
  • Supplies

These expeditures are generally used for:

  • Drilling, perforating, and cleaning wells.
  • Preparing the surface site prior to drilling.
  • Construction derricks, tanks, pipelines, and other structures erected in connection with drilling, but not including the cost of the materials themselves.

The fundamental test is defining the salvage value of the item. If the item does not have a salvage value, it is an intangible.

Intangible drilling and development costs do not include the following:

  • Tangible property ordinarily considered as having salvage value.
  • Wages, fuel, repairs, hauling, supplies, etc., in connection with equipment facilities or structures not incident to or necessary for the drilling of wells, such as structures for storing oil.
  • Casing, even though required by state law.
  • Installation of production facilities.
  • Oilwell pumps, separators, or pipelines.

Detailed cost analysis[1]

It is usually desirable to provide more cost detail than the general summary in Fig. 1. A sample of a detailed summary is shown in Fig. 2

Factors considered in the detailed cost analysis will be presented in the AFE page. The cost divisions presented in Fig. 1 will be used. These factors are heavily dependent on company drilling philosophy and, as such, may not apply to all companies.

References

  1. Adams, N. and Charrier, T. 1985. Drilling Engineering: A Complete Well Planning Approach. Tulsa, Oklahoma: PennWell Publishing Company.

Noteworthy papers in OnePetro

External links

See also

Well planning

PEH:Introduction_to_Well_Planning